Design and construction of a new polyisocyanurate plant, including an office area.
This industrial project, in the turnkey formula, involved to coordinate several professionals and customer needs to meet the requirements of the factory process, the City and LEED standards. The project is waiting to receive LEED Gold Certification.
Project services
- Identification and understanding of the challenges
- Design and coordination with the professionals
- Planning and monitoring of the construction schedule
- Cost control
- Construction and realization of the project
- Coordination and installation of the electromechanical and client equipment
- Management of post-construction guarantees
- LEED certification management
Client
Conax Properties Ltd.
Location
3100, rue Kunz, Drummondville
Year
2015
Budget
$16.6M
Structure
Wood, Steel